Colour-code the process water lines (the entire
length).
Design the tapping points in accordance with
TrinkwV 2001 Art. 17 Para. 2 Clause 3.
Identify the taps with the notice "Not drinking
water".
The drinking water must be fed in in
accordance with the regulations in DIN/EN
1717. The customer provides for this in the
case of the water recycling system.
Thermally insulate cold water pipes (drinking
water feed).
Installation room
The required room height is 2.10 m minimum.
The installation location must be frost-proof,
dry, protected against the weather and well
aerated and ventilated.
Set up the water recycling system on a level
surface and align it.
With regard to the load-bearing capacity of the
installation surface, please refer to the
system's weight as given in the
dimensioned drawing.
There must be a floor drain in the installation
room. Refer to EN 12056 "Drainage
systems".
It is not compulsory to use a water meter. We
recommend installing one water meter in
the process water pipeline and one in the
drinking water feed. This enables you to
determine from the difference the savings
of the water recycling system. It is possible
to connect the meter to the system's
controller.