Installation and start-up
9.1

Initial start-up

1.
Install the mounting plate and pump in the required location and installation scenario.
Ä Chapter 7 'Assembly and connection' on page 38
2.
Make the hydraulic connections.
Ä Chapter 7.2.1 'Hydraulic installation' on page 43
3.
If necessary, make the electrical connections for signal inputs.
Ä Chapter 7.2.2 'Electrical installation' on page 49
4.
Connect the mains plug (fitted at the factory) to the power supply.
5.
Switch on the pump using the 'ON/OFF switch'
6.
Select language:
Ä Chapter 9.2 'Language selection' on page 139
7.
Set operating mode: See
8.
Vent the system: See
9.
Perform calibration on initial start-up:
Ä Chapter 9.4 'Calibration on initial start-up' on page 141
See
MAN046939 Rev. 6-10.2021
CAUTION!
When the pump is started for the first time, NO ACCESS CODE is
activated.
To prevent misuse of and/or unintentional adjustment of the system
parameters, the pump software must be protected by the integrated multi-
stage [Access code]. We recommend that you activate the [Access code]
during initial configuration and only disclose the passwords to authorised
persons:
Ä Chapter 8.8.4 'Access code' on page 93
Setting an access code also protects the pump against unauthorised
access using a smartphone connected via Bluetooth. If a pump is
not protected, all its functions can be accessed using the EcoAPP.
If an access code has been defined in the pump, this is visible in the
EcoAPP after the access code has been entered there.
Ä Chapter 8.7 'Operating mode' on page 67
Ä Chapter 9.3 'Venting the metering pump' on page 140
.