Installation Of The Coping And Box Duckboarding; Installation Of The Coping - BWT myPOOL POOL'N BOX Instrucciones De Montaje

Tabla de contenido
Idiomas disponibles

Idiomas disponibles

9.

INSTALLATION OF THE COPING AND BOX DUCKBOARDING

9.1

Installation of the coping

Note the layout of various pool coping modules in
Orient them so that the grooved surface is facing up around the periphery of the pool. Allow a 10 mm
overhang over the inside the pool (measured from the pool wall). Take the time necessary to ensure that
the coping modules are correctly aligned and that the overlap is even.
REF
QTY
P
2
Q
1
R
1
S
1
T
1
U
2
Working from underneath, screw the coping modules in position using 2 A4 SS torx hinge screws 6 × 20
(bag G) per corner coping support bracket, and 4 screws of the same type for each lefthand and righthand
coping bracket (that is a total of 88 screws).
Working from underneath, screw the wooden coping support brackets into position, taking care to insert
the screw in the centre of the bracket to avoid any risk of splitting. Use 2 A2 SS torx countersunk screws 5
× 60 threaded over 35 mm wooden coping, that is, a total of 30 screws.
WOODEN POOLS
Figure 31 – Location of the coping modules
Pine coping module 1838 x 195 x 28 mm
Pine coping module 2015 x 195 x 28 mm /righthand cutout
Pine coping module 2015 x 195 x 28 mm /lefthand cutout
Pine coping module 2248 x 195 x 28 mm /righthand cutout
Pine coping module 2248 x 195 x 28 mm /lefthand cutout
Pine coping module 2370 x 195 x 28 mm
BWT myPOOL POOL'N BOX
Figure
31.
DESCRIPTION
2021/02 - Version: D Code : 37311
33/48