5. OPERATION

Should any problem occur, immediately turn the power to the machine OFF until the
problem has been rectified.
Before operating the machine, check that the machine has been installed in
accordance with the instructions and procedures specified in this manual. If the
machine is not installed correctly, fire, electric shock, injury or malfunction may
occur.
Ensure that all warning labels are visible and legible at all times.
To ensure safe operation of the machine, ensure that the pre-service and
maintenance checks have been carried out. Failure to perform the pre-service
maintenance checks could result in unexpected accidents.
5-1

Pre-Service Check

Check the following items before commencing operation.
If any problem is found, rectify the problem before continuing.
5-1-1

Safety Check (before power on)

1.
Is any part of the Mains Cable or plug excessively warm.
2.
All warning labels are attached and legible.
3.
All level adjusters are adjusted properly and the machine is stable.
4.
The Play Zone area is established as specified.
5.
Power cable and Communication cable are routed safely and not liable to cause a
person to trip over them.
6.
Guns are secure and free of any damage.
7
The Jointbox is installed securely to both the Monitor Cabinet and the Control Assy.
8.
Pedal Assemblies are secure. (There must be no space between the Pedal Assy
and the floor.)
9.
Speaker boxes are installed securely to the Monitor Cabinets.
10.
Header Assy is installed securely to the Speaker boxes.
46