Checks Before Commissioning - Zumtobel ONLITE central eBox Serie Puesta En Operación Rápida

Tabla de contenido
Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 72

Checks before commissioning

10
Checks before commissioning
Before commissioning of the ONLITE central eBox system can begin, you must first perform the following checks
in accordance with HD 60364-2 Section 61:
1. Inspect the permanent electrical system.
2. Test and measure the continuity of the conductors.
3. Test and measure the insulation resistance of the electrical system.
4. Test and measure the protection provided by automatic switch-off of the power supply (check upstream
fuses).
5. Test and measure the voltage polarity.
If an error is identified during testing and measurement, proceed as follows:
1. Rectify the error.
2. Repeat the checks (including any previously performed checks that may have been influenced by the error).
Checks before commissioning
Done
26
ONLITE central eBox, Quick commissioning 3.0 | 03.2019 | en
Tabla de contenido
loading

Tabla de contenido