1-8. Installing Distribution Joint Kit (for Triple)
(APR-RTP280AGB)
●
Check the system combination before installing the
distribution joints.
●
Three indoor units must be installed within the
GB
same room.
●
Use the supplied tube connectors to adjust the
tube sizes of the distribution joints.
How to Install Distribution Joints
FR
Use the supplied distribution joints to complete refrig-
erant tubing work.
Install distribution joints so that the tubes are horizon-
tal after the branch point.
DE
Orientation of distribution joints
Only the distribution joints are
horizontal with respect to the ground.
IT
The collective tubes are vertical with
respect to the ground.
PT
GR
ES
<Gas tube side>
Length requirement for strainer on main
distribution tube side
Attach a straight tube 500 mm or longer to the
main tubing side of the distribution joint (for
both liquid and gas tubing).
Tubing insulation
Be sure to apply thermal insulation to both the
liquid and gas tubing.
Depending on the conditions inside the ceiling,
condensation may form on the insulation mate-
rial. If high temperatures and high humidity are
expected to occur inside the ceiling, add glass
3
wool (16 – 20 kg/m
, with a thickness of 10 mm
or more) to the below insulation materials and
apply sufficient thermal insulation.
DC̲Inverter̲Eng.indd 16
DC̲Inverter̲Eng.indd 16
The collective tube and
distribution joint are horizontal
with respect to the ground.
Collective tube
Distribution joint
Only the distribution joints are horizontal with
respect to the ground. The collective tubes
are vertical with respect to the ground.
The collective tube and distribution
joint are horizontal with respect to
the ground.
<Liquid tube side>
INCORRECT
Distribution joint insulation material (supplied)
•
Use the supplied insulation material.
•
The supplied insulation material include only a
tape for temporarily fastening.
•
Use insulation material or other material to
seal the joining lines so that there are no gaps.
•
Use vinyl tape or similar means to seal and
fasten the insulation materials in place.
Seal securely with vinyl tape (4 locations)
Refrigerant tubing (field supply)
Tubing insulation material
(field supply; thickness of more than 10 mm)
Tubing insulation material must be able to withstand
temperatures of at least 120C.
Refrigerant tubing (field supply)
16
Collective tube
Distribution joint
Be sure to install so that
the tubes are horizontal
after the branch point.
2007/07/25 13:21:36