Fagor PS-20/140 M Manual De Instrucciones página 28

Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 33
6 PREVENTIVE MAINTENANCE
All maintenance operations must be carried out by qualified staff.
BEFORE ALL MAINTENANCE WORK, CUT OFF THE MACHINE POWER SUPPLY AT THE
INSTALLATION CIRCUIT BREAKER AND CHECK THAT THERE IS NO VOLTAGE.
CAUTION, IF THE WORK IS CARRIED OUT IMMEDIATELY AFTER WORK, THE MACHINE
MAY STILL HAVE VERY HOT PARTS, THEREBY CREATING A BURN RISK.
DURING MAINTENANCE
EQUIPMENT (gloves, no-voltage tester, etc.)
The safety devices must not be removed (even temporarily) or modified. When in doubt,
contact your dealer's technical department giving the machine model and serial number.
NEVER SPRINKLE WATER ON THE MACHINE
An alarm can be programmed on the maintenance menu to warn that preventive maintenance
should be carried out (see section 3.4). This alarm is programmable per operating hour, so
after the programmed number of working hours, the alarm will appear on the display each time
the machine is started until a new maintenance programme is defined or the alarm is
deactivated.
Below is a table summarising the preventive maintenance that must be carried out and how
often:
Checking of all machine safety devices: Emergency stop, safety plate, handle
safety, safety thermostat, earthing (electric).
General cleaning: inside, in the frames (lint and grease), ventilation fan, stripper
blades, feelers, pressure switch piping.
Check the condition of the feelers and their position (see section 4.5)
Replacement of the entire guide band set (See section 4.3)
Check and tighten electrical connections on the cut-off switch, the heating
contactor and the heating elements
WORK, WEAR SUITABLE
Check and maintenance points
PERSONAL
PROTECTION
Frequency
(hours)
500
22
loading

Este manual también es adecuado para:

Ps-20/160 mPs-20/200 m