Configuration Of The Installation; Configuring The Bow And / Or Stern Thruster; Setting For The Size Of The Thruster; Setting 12 Or 24 Volt - Vetus STE9524D Instrucciones De Instalación

Ocultar thumbs Ver también para STE9524D:
Tabla de contenido
Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 89
7

Configuration of the installation

Both the panels and the bow thruster / stern must be configured cor-
rectly.
7 .1

Configuring the bow and / or stern thruster

Bow thruster
If only one (1) retractable bow thruster is installed configuration is
not necessary.
Bow thruster + Stern thruster
The default configuration is for use as a bow thruster.
Only the configuration of the stern thruster must be adapted.
• Remove the cover from the junction box by removing the front 'E'
and the screws.
The DIP switches must be configured as
shown in the drawing.
7 .2

Setting for the size of the thruster

7 .3

Setting 12 or 24 Volt

The setting for the voltage must match the
voltage on board.
vetus® Installation instructions Retractable Thrusters
Stern thruster
If only one (1) retractable stern thruster is installed configuration is
not necessary, but consider the stern thruster panels as bow thruster
panels when configuring.
185 mm
12 V
24 V
12 Volt
ENGLISH
E
150 mm
250 mm
24 Volt
45
020584.01
Tabla de contenido
loading

Este manual también es adecuado para:

Ste5512dSte6012dSte5524d