11. Test run
11-1. Before a test run
After the wiring work has been completed, measure the insulation resistance, and make
- Failure to do so may result in electric leakage, malfunction, or fire.
Turn on the power at least 12 hours before starting operation. Keep the power turned on
throughout the operating season.
- Insufficient energizing will result in malfunction.
・Before performing a test run, turn off the power to the outdoor unit, and disconnect the power cable from the power
supply terminal block to measure the insulation resistance.
・Measure the insulation resistance between the power supply terminal block and the earth with a 500 V ohmmeter,
・
and check the compressor for a earth fault.
・While the unit is turned on, the compressor will remain energized even when it is stopped.
・
immediately after installation or when the main power to the unit has been turned off for a long time because of the
stagnation of refrigerant in the compressor.
・By turning on the main power and energizing the unit for 12 hours or longer, the refrigerant in the compressor will
evaporate and the insulation resistance will rise.
・Do not apply an ohmmeter voltage to the terminal block for transmission cables. Doing so will damage the control
board.
・Do not measure the insulation resistance of the transmission terminal block of the unit remote controller.
・Check for refrigerant leakage and for loose power cables and transmission cables.
・Check that the liquid and gas side service valves are fully open. Tighten the valve caps.
・Check the phase order of the power supply and the interphase voltage. If the voltage is out of the ±10% range, or if
the voltage imbalance is more than 2%, discuss the countermeasure with the customer.
・When a transmission booster unit is connected, turn on the transmission booster unit before turning on the outdoor
unit. If the outdoor unit is turned on first, the refrigerant circuit connection information will not be properly verified. If
the outdoor unit is turned on first, turn on the transmission booster unit and then power reset the outdoor unit.
・When a power supply unit is connected to the centralized control transmission cable, or when power is supplied
from a system controller with a power-supply function, perform a test run with the power supply unit being
energized. Leave the power jumper connected to CN41.
・When power is turned on or after power recovery, performance may degrade for approximately 30 minutes.