Chapter 2. How to Configure and Program the Control
Raise Fill Temperature—The 3rd water valve opens only to increase the bath temperature to the
desired temperature while the machine is filling.
Lower Fill Temperature—The 3rd water valve opens only to decrease the bath temperature to
the desired temperature while the machine is filling.
Level or Liquor Ratio
2.2.7.
The amount of water in the machine for each bath step is normally controlled by a pressure
transducer. Optionally, some models can be equipped with a flow meter to measure the amount of
water that flows into the machine.
Water Level
2.2.7.1.
Level 1, 2, and 3—Fill to the level that was configured for Level 1, 2, or 3.
User Defined—Fill to a user-defined level for this step only. Units are inches or centimeters.
Liquor Ratio
—Machines equipped with a flow meter can fill to a programmed ratio of water
2.2.7.2.
to goods. This ratio is defined as a programmed amount of water for the programmed nominal
load weight for each formula. When the machine is loaded, the operator enters the actual weight
of the load, then the machine calculates the desired number of flow meter counts to achieve the
programmed ratio.
For each step that will use liquor ratio, touch the Level button, then the User Defined button. On
the Water Level screen, enter the number of water units desired for the programmed nominal
weight for the formula. This value must be more than the value configured for Water Level 3.
1. Touch the Nominal Weight button
Figure 25: Nominal Weight button
2. Touch the Add Formula button on the Program Nominal Weight
the formulas that use the flow meter.
PELLERIN MILNOR CORPORATION
(Figure
25) to go to the Program Nominal Weight screen.
32
(Figure
26) screen to enter