UNIT INSTALLATION
6.2.2 Removing indoor unit electrical box
!
D A N G E R
Disconnect the unit from the power supply before touching any
of the parts in order to avoid an electrical shock.
Do not touch the switch for DHW tank heater operation when
handling the electrical box. Keep the position of this switch in
factory setting position ("Automatic" operation).

Open the electrical box cover
1 Remove the indoor unit front cover.
2 Unscrew the 2 front screws of the electrical box cover and
then, open it.
!
C A U T I O N
Take care with the electrical box components in order to avoid damaging
it.
21
PMML0573 rev.1 - 07/2021
Switch
Indicative
(SW1)
label
6.3 INSTALLATION OF INDOOR UNIT
?
N O T E
Please, try to perform all this procedure following all the steps in the exact
order in which they are presented below.
Installation procedure
1 Space heating pipes connection
2 Drain pipes connection
3 DHW pipes connection
4 Refrigerant piping connection
5 Power and transmission wiring connection
6 Levelling procedure
7 Test and check
6.3.1 Space heating pipes connection
The unit is factory supplied with two shut-down valves to be
connected to the water inlet/outlet pipe. With these shut-down
valves it is very practical to connect the indoor unit to the
heating system by using the factory supplied gaskets just below
the valves (2-3HP: G 1"; 4-6HP: G 1-1/4"). Then, the space
heating installation can be carried out.
Shut-off valves
Gaskets
6.3.2 DHW pipes connection
The connection between the DHW installation and the DHW
connections of the indoor unit must be done taking into account
the following considerations:
1 Install a pressure and temperature relief valve at the DHW
inlet connec tion (as close as possible to the tank) to provide
the following functions.
Pressure protection
Non-return function
Shut-down valve
Filling
Draining
If not, an specific device for each function should be installed.
2 Install also a shut-down valve (field supplied) in the DHW
outlet connection, in order to make easier any maintenance
work.
?
N O T E
For more details, refer to the section
(space heating and
DHW)".
"7.2.3 Hydraulic circuit checking
loading