3.1
Materials and Tools
NOTE Salt not included. See Section 4, Pool Water Preparation.
Installation Materials Furnished Needed
Nature
Fusion Soft
2
Vessel with 2"-2½" (5 - 6.3 cm) Universal Unions
Sensor with 16 ft (4.88 m) Cable and O-ring
Universal Union Nut (to secure sensor)
16 ft (4.88 m) DC Power Cord
Installation and Operation with Warranty Information
FUSIONM or APUREM Power Pack (Sold separately)
Power Pack Housing with User Interface Control
Two (2) Wire Nuts
Installation Template
3.2
Installation Requirements
Decide where to install the Nature
The vessel must be installed on a 17" (43 cm) length of pipe.
The vessel must be installed on the existing pad or a concrete slab to support the weight.
The vessel must be installed as the last piece of equipment in the circulation plumbing system just before the pool
with the Nature
side as the inlet and the salt chlorinator side as the outlet. The inlet and outlet are clearly marked
2
on the vessel.
The vessel must be installed downstream from the heater or heater damage will occur.
If the vessel is installed below the pool water level, it must be installed with a check valve. The check valve will
isolate the vessel and prevent pool draining during installation, cell change or cartridge change.
If plumbing size is greater than 2" (5 cm) diameter or if flow rates are greater than 120 gpm (455 lpm), the vessel
must be installed in a bypass configuration (see Section 3.5).
If the vessel is used with water feature line system, it must be installed in a split-return configuration or vessel
damage may occur (see Section 3.6).
Never install the Nature
backwash valves, or other sensitive metallic components are installed, consult your dealer for recommendations
on your particular system.
3.3
Anchoring the Vessel to the Equipment Pad
In some areas, for example Florida, building codes require that all appliances be securely fastened to the equipment
pad in order to withstand high wind pressures created by hurricanes. Please follow all local codes and standards.
Zodiac
Nature
®
Fusion Soft.
2
Fusion directly into copper plumbing as pipe damage may occur. If brass or bronze
2
|
2
Fusion soft
Installation and Operation Manual
®
PureLink
with Power Center (Optional - Sold separately)
TM
AquaLink
RS PureLink power center (Standard or Breaker)
®
Two (2) Wire Nuts
Installation Template
Tools Needed for Installation
Tape Measure
Phillips & Flathead Screwdrivers
Pliers
Hacksaw
Voltmeter to determine line voltage of AC wiring to power
supply
Electric Drill Motor and 1/4" (0.6 cm) masonry drill bit for
mounting power supply on block or stucco wall
An NSF
approved All Purpose Cleaner Primer
®
An NSF approved All Purpose Cement (such as Weld-On
794™, 793™)
®