20. Push and slide the exterior braided armor up the cable so that its cut end is tight against the
21. Install the clamp disassembled in step 11. Tighten the screws evenly so that the clamps tighten
22. The cable is now ready for installation and grounding.
64084463
|
03
|
12/2017
the gland should appear as shown in Figure 2-45; here, the cable and gland assembly is
shown removed from the terminal for clarity.
Figure 2-45: Inner Armor and Foil Pressed into Body of Cable Gland
cable gland. Tidy up any stray wires, using a small screwdriver to push them into the back of
the outer part of the gland.
symmetrically on the outer armor. Note that the outer drain wire should emerge between the
clamp and the cable gland. (For clarity, Figure 2-46 shows the gland assembly separate from
the terminal enclosure.)
Figure 2-46: Exterior Braided Armor Clamped in Place
Figure 2-47: Cable and Cable Gland Installed in Enclosure