4.3 Install the pump

4.3.1 Mechanical installation

Check the following before installation:
• Use a concrete of compressive strength class
C12/15 which meets the requirements of expo-
sure class XC1 to EN 206-1.
• The mounting surface must have set and must
be completely horizontal and even.
• Observe the weights indicated.
Install the pump set
For examples of horizontal and vertical installations,
see
Figure 13
(page 342).
Check that the foundation has been prepared in ac-
cordance with the dimensions given in the outline
drawing/general arrangement drawing.
Type
Motor Size Number of
A
Up to 132
B
From 160
to 200
From 160
to 280
C
250
D
Up to 132
E
From 160
to 280
1. Position the pump set on the foundation and
level it with the help of a spirit level that is
placed on the discharge port.
The permissible deviation is 0.2 mm/m.
2. Remove the plugs covering the ports.
Type of
Poles
Fastening
2– and 4–
Mount on
pole
ground us-
ing the vol-
ute casing
feet.
2–pole
Mount on
ground us-
ing the
4–pole
pump and
motor feet.
Shims are
required
under the
pump and
motor feet.
2–pole
Mount on
ground us-
ing the
pump and
motor feet.
Shims are
required
under the
pump and
motor feet.
2– and 4–
Mount on
pole
ground us-
ing the vol-
ute casing
feet.
2– and 4–
Mount on
pole
ground us-
ing the mo-
tor feet
3. Align the pump and piping flanges on both sides
of the pump. Check the alignment of the bolts.
4. Fasten the piping with bolts to the pump. Do not
force the piping into place.
5. Use shims for height compensation, if necessa-
ry.
6. Tighten the foundation bolts evenly and firmly.
Note:
• If the transmission of vibrations can be disturb-
ing, provide vibration-damping supports between
the pump and the foundation.

4.3.2 Piping checklist

Check that the following are adhered to:
• The suction lift line has been laid with a rising
slope, at positive suction head line with a down-
ward slope towards the pump.
• The nominal diameters of the pipelines are at
least equal to the nominal diameters of the pump
ports.
• The pipelines have been anchored in close prox-
imity to the pump and connected without trans-
mitting any stresses or strains.
CAUTION:
Welding beads, scale and other impuri-
ties in the piping damage the pump.
• Free the piping from any impurities.
• If necessary, install a filter.

4.3.3 Electrical installation

1. Remove the screws of the terminal box cover.
2. Connect and fasten the power cables according
to the applicable wiring diagram.
For wiring diagrams, see
The diagrams are also available on the back of
the terminal box cover.
a) Connect the ground (earth) lead.
Make sure that the ground (earth) lead is longer
than the phase leads.
b) Connect the phase leads.
3. Mount the terminal box cover.
NOTICE:
Tighten the cable glands carefully to ensure pro-
tection against cable slipping and humidity en-
tering the terminal box.
4. If the motor is not equipped with automatic reset
thermal protection, then adjust the overload pro-
tection according to the list below.
– If the motor is used with full load, then set
the value to the nominal current value of
electric pump (data plate)
– If the motor is used with partial load, then set
the value to the operating current (for exam-
ple measured with a current pincer).
– If the pump has a star-delta starting system,
then adjust the thermal relay to 58% of the
nominal current or operating current (only for
three-phase motors).
en - Original instructions
Figure 14
(page 343).
19