5 Installation
42
Conergy IPG series central inverters automatically adjust their
switch-on waiting time to local conditions. This prevents ineffective
attempts to connect to the grid (e.g. at sunset).
A waiting time of a few minutes is observed when switching on
after grid malfunctions. If switched off due to insufficient power
input and the solar generator voltage then goes back up above the
switch-on threshold, the switch-on waiting time will be about four
minutes.
After a self-test of approx. 5 seconds, the current operating status
of the inverter is indicated using the 4 signal lamps on the front
door.
The operating frequency of central inverters lies within a clearly
audible range. The noises which are perceived as a type of
screeching, hissing or squeaking are typical of the device and
represent no impairment to operation.
Display
Meaning
On
Grid feed-in mode or grid connection waiting time
SG
Status of solar generator voltage and output
Grid
Status of grid connection
Fault
Fault condition
Symbols representing the LED indicators
LED is lit
LED is flashing
LED is off
The status of this LED indicator has no significance for the
message currently displayed.
Initial state before switching on
| All LED indicators are off.
| No power supply to the internal electronics.