Siemens RVL482 Instrucciones De Montaje página 36

Ocultar thumbs Ver también para RVL482:
Tabla de contenido
Idiomas disponibles
  • ES

Idiomas disponibles

  • ESPAÑOL, página 254
en
Wrong
Commissioning
Preparatory checks
1. DO NOT switch on power yet.
2. Check wiring according to the plant connection diagram.
3. Ensure correct position and location of levers by turning the fixing screws. Refer to illustra-
tion on the lateral wall of the controller:
4. Insert unit in the base until stop is reached. Marking TOP must be at the top!
5. Tighten fixing screws alternately.
6. Check controlling element (seat or slipper valve): See if
– it is correctly installed (observe direction of flow indicated on the valve body)
– the slipper travels in the correct angular range (note position indicator)
– the manual lever is disengaged
Building Technologies
For latest prices and delivery to your door visit MyTub Ltd - www.mytub.co.uk - [email protected] 0844 556 1818
Place tongues correctly – they may not be
inside the cutout!
Correct
74 319 0619 0 a
17.04.2008
36/288
Tabla de contenido
loading

Tabla de contenido