Selecting The Anchors; Assembly; Set Up And Anchoring The Lift - Nussbaum POWER LIFT HL 2.50 NT Instrucciones De Servicio

Tabla de contenido
Idiomas disponibles
  • ES

Idiomas disponibles

4.4

Selecting the anchors

Without floor cover
Anchor type
(screed/tiles)
Heavy duty anchor
Liebig/Strongtie
BM 16-25/100/40
Fischer
FH 24/100 B
Hilti
HSL-3-G M16/50
Injection anchor
MKT
VM2-A105M16-30/160
Hilti
HIT-V-5.8 M16 x 200
Highbond
Fischer
FHB 16x160/30
4.5

Assembly

Follow the instructions enclosed in the anchor packaging.
i
4.6

Set up and anchoring the lift

i
On-site provision of suitable auxiliary materials
(e.g. forklifts, crane, etc) are to be made avail-
able for unloading the lift and for assembly.
Before setting up the lift, the operating company
must ensure or make a sufficient foundation. For
this, a normal reinforced concrete floor with a value
of a min. C20/25 is required.
The minimum foundation thickness (without screed
and floor tiles) is to be taken from the foundation
plan in this document.
In our plans, we inform of the minimum specifica-
tions for the foundation, however local conditions
(e.g. underground, floor quality, etc.) are outside of
our responsibility.
In special cases, the design of the installation loca-
tion must be individually specified by planning ar-
chitects and statics experts.
Open air foundations must be made to frost depth.
52
i
Similar value anchors and other known brands
With floor
of anchor manufacturers can be used when
covering
considering the conditions.
(screed/tiles)
Anchor length
Depends on
Floor covering
i
The operating company of the lift is solely re-
sponsible for the set up location.
If the lift is to be assembled on an existing con-
crete floor, cement quality and strength are to
be checked beforehand. In case of doubt, make
a test bore and insert a heavy-duty anchor. Then
tighten the anchor to the manufacturer recom-
mended torque.
After inspection within the anchor zone of influence
(see technical data sheet of the anchor manufac-
turer), if there is visible damage (hairline cracks,
cracks or similar), or if the required torque cannot
be applied then the set up location is unsuitable.
The following preparation and work steps are to be
done:
• To reach a higher level of protection against hu-
midity from the workshop floor, a thin PE foil should
be put between the workshop floor and column
base plate (2) before anchors are placed. Also,
the gap between the base plate and workshop
floor should be silicone sprayed after anchoring.
Version 1.0
20110002 POWER LIFT HL 2.50 NT - HYMAX HL 5000 PH OPI
022
Tabla de contenido
loading

Este manual también es adecuado para:

Hymax hl 5000 ph

Tabla de contenido