4

Commissioning

4.1
Connecting and disconnecting the inverter
Connecting
Switching Off
4.2
Commissioning
IPE 2700 - 5000 SN 05
CAUTION
x Ensure proper mechanical and electrical installation before commissioning the in-
verter.
x Check the cables to ensure that they are in sound condition.
x Always disconnect the mains connection first by switching off the corresponding
mains fuse and before disconnecting the solar generator side by opening the DC
load break switch.
x The Multi-Contact MC4 connectors on the solar generator side must not be dis-
connected under load. First turn the DC load break switch to position 0.
NOTE
The inverter is supplied from the mains. The inverter switches on automatically when
sufficient solar generator output is available. Corresponding switch-on and switch-off
thresholds have been defined for this purpose.
1. Establish the grid connection via the external circuit breaker.
2. Switch on the solar generator voltage by closing the DC load break switch (swit-
ching position 1). The inverter starts operating when the input voltage level is
adequate.
1
1 DC Load Break Switch
The operating LED lights up in accordance with the operating state.
The commissioning menu opens when the inverter is connected for the first time.
1. Open the grid connection by switching off the circuit breaker.
2. Disconnect the solar generator side by opening the DC load break switch (switch
position 0).
The commissioning menu comes up automatically when the inverter is connected for
the first time. It helps you make the standard settings.
Commissioning
39