4.3. Electrical connection

salva
The oven is supplied without a plug. The customer shall be responsible
for supplying a plug.
The oven must be connected to the mains by a qualified electrician.
Making a 400 V three-phase connection requires three phases + neutral +
earth; for 230 V three-phase, it would be three phases + earth; and if for
230 V single phase, it would be two phases + earth.
It is important that the installation side has a C curve magnetothemic
switch of suitable amperage, in accordance with the consumption of the
oven and the installation cables of the premises. A 0.3A leakage current
differential circuit breaker is also required.
The cable section must be suitable for the power of the oven, in accord-
ance with local regulations.
The values for the magnetothermal switches, cable cross-section and
plug are shown in the table below.
Power
kW
Circuit
breaker
7
2 x 32 A
Connection
Power
230V
kW
3 phases + ground
Sections
Circuit
of the
breaker
cables
4 x 4
7
3 x 32 A
mm
(3+T)
-78-
MONOPHASE
Connection
230V
2 phases + ground
Sections of the cables
3 x 6 mm
(2+T)
2
TRIFÁSICO
Connection
3 phases + neutral + ground
CEE
Sections
con-
Circuit
nector
breaker
cables
plug
5 x 2,5
32 A
3 x 16 A
2
(3P+T)
(3+N+T)
Montaje_Labe_17_(c-f-i)260617
CEE
connector
plug
32 A (2P+T)
400V
CEE
con-
of the
nector
plug
16 A
mm
2
(4P+T)