2. Attach the cleanout body securely to the leader pipe using no hub (standard), or
push-on (-P), for cast iron, and solvent weld or no hub for PVC.
Concrete
3. The finished surface of the cleanout top should be protected during all phases
of construction by the use of the plastic cover provided. Adjust the top of the
cleanout with the plastic cover in place by screwing it into the cleanout body until
the top of the cover is flush with finish floor grade. Bottom of plastic top assembly
should sit tight against the anchor flange or optional stainless steel membrane
clamp ensuring that no concrete seeps into the cleanout assembly. Apply
petroleum jelly around outer edge of plastic cap for ease in post-pour removal.
Make sure cover is snug but do not over tighten.
4. Cleanout should be set and leveled in place with the top adjusted to the
height of the finished floor before concrete sub-floor can be poured. Concrete
should be poured flush to top of cleanout body.
5. When installing on-grade slab installation, it is recommended to use a bead of
silicone around the last thread of the top assembly.
Cleanout Body
Recessed Slot
Leader Pipe
Recessed Slot
4
Concrete
Bubble Level