12.2 BLOWER MOR/GOR ATEX 3GD INSTALLATION
Units supplied with standard set-up are ready to be installed in the
horizontal position (MOR).
The feet have holes for fixing; use the holes and choose the
appropriate type of screw.
Remove the protection on the ports before checking the rotation
direction and before final connection (A).
To connect the unit to the piping, remove the flange from the
silencer housings (B).
Screw the flanges to the pipes and clean from any impurities.
Refit the flanges on the silencer housings. Provide for a hose, as
per the initial diagrams.
Given the likelihood of an explosive atmosphere, the use of pressure measuring instruments is advisable (but not
NOTE FOR THE
compulsory) in order to check that the difference between the delivery and suction pressures respects the values
USER
given in the "SPECIFICATIONS" and on the machine's rating plate.
12.3 BLOWER GOR ATEX 2G INSTALLATION
Operations to be carried out for installing the blower:
Fix the base and unit's vibration dampers to the system's structure.
Remove the protection from the manifolds (A).
Use flexible sleeves to connect the unit to the system.
Check the motor rotation direction.
Connect the pipes permanently.
The blower is arranged for the installation of measurement/control systems in order to prevent machine faults that can produce
potential sources of triggering:
Pressure sensor
Temperature sensor