Installation
4.1
Requirements for the installation surface and location
Installation surface requirements
g
Load capacity, fitness for use, durability in accordance with DIN EN 206
g
Evenness tolerance in accordance with DIN 18202 Table 3 Line 3
g
Concrete strength minimum C25/30
g
No slope towards the foundation
g
Absorbent surfaces or underlying elements cause significant corrosion – DENIOS accepts no liability
in this case
g
The product may be anchored
Installation location requirements
g
Installation location is outdoors
g
Installation location is only accessible by authorised personnel
g
An Ex zone may need to be observed at the installation location
g
No snow drifts can form on the product
g
Forklifts and other transport vehicles and lifting equipment cannot drive into the product
g
Position away from internal roadways or use impact protection
g
Ensure that no nearby heat sources can heat up the product's surfaces
g
Install well away from pits, drains or outflows as well as low-lying areas
g
Install away from rescue routes
g
Fire extinguisher is available and easily accessible
Structural requirements
Minimum distances must be observed when storing acutely toxic gases (H330) or flammable gases
(H221– 220):
g
5 m around the pressurised gas cylinders to neighbouring plant and equipment
4.2
Assembly instructions
Follow the sequence given in the instructions for assembly:
1. After fitting the side walls, align the product using a suitable tool (e.g. spirit level).
2. After alignment, anchor the product with heavy duty anchors, 12 mm (not included in the delivery).
3. Fit the remaining components.
276267_GSN_Operating-instr_002_INT
42/100
Installation