6.5 FUNCTION AND SAFETY CHECK AND TEST
At least once a year, the following check and test should be done by the biomedical engineering department or other qualified
personnel:
§
Check of the connectors and mains supply cord conditions;
§
Visual check of the mechanical protections;
§
Check of the protections against the danger due to liquid's pouring, dripping, moisture, liquid's penetration, cleanliness,
sterilization and disinfection.
§
Check of the Equipment's Datas on the Label
§
Check of the availability of the Instruction's Manual
§
Check the functioning of the H.F. output controls
§
Check the uniformity of the resistance through the surface of the patient plate.
§
Test the earth conductivity resistance.
§
Test the earth leakage current.
§
Test H.F. leakage current.
§
Control of the neuromuscular stimulation.
§
Control of the accuracy of the output power.
Manuale d'Istruzione / Instruction's Manual / Manual de Instrucciones
MA126IGBa
DIATERMO 106
33