2. Installation instructions

2.1 Installation

Before installing the BA backflow preventer, check that:
• The BA device must be easily accessible to allow inspection,
maintenance and replacement of defective components
• Test points must be provided to enable the system to be
tested without difficulty
• It must not be installed in areas subject to flooding
• It must be installed in a ventilated area (non-polluted
atmosphere)
• The relief system must be capable of discharging the relief
flow
• It must be protected against frost and extreme temperatures
• It must be installed horizontally with the relief port facing
down
• The funnel, with air gap, must be connected to the relief
network
• It can only be used for potential backflow not exceeding the
relief capacity
The protection device must be installed by a qualified technician.

2.2 Commissioning

1. Flush and fully drain the upstream pipes before installing the
BA protection device with its accessories.
2. Install the BA protection device with its accessories, in the
direction of flow, as follows:
• Upstream: one type SOCLA or equivalent Butterfly valve,
• Between the upstream valve and the device: one type Socla
Y333P or equivalent mesh strainer with drain cock.
• Downstream: one type Socla or equivalent Butterfly valve.
Adhere to the installation diagram below:
Watter
supply
inlet
Ground, oor, walkway
Sever
Drain
conduit
5
Celling, vault, beam...
LT
ØF
The protection system must be assembled without forcing
the inlet and outlet fittings
3. Fit the funnel on the BA protection device. It is designed
to be connected to a pipe (e.g. PVC discharge pipe) with
external diameter equal to the diameter shown (see

2.3 Filling with water:

During filling with water:
• The upstream and downstream valves are closed,
• Open the upstream valve slowly, to bring the BA protection
system up to pressure gradually,
• Open and close tap No. 1 and then taps 2 and 3
respectively to drain the BA protection device,
• Open the downstream valve slowly, to commission the BA
protection system.
Once the BA protection system has been commissioned, it:
• Ensures that the downstream water requirement is met
• Protects the upstream network against the risk of pollution
PRECAUTIONS:
• In the case of an upstream diversion in the area right in
front of the backflow preventer, it is necessary to install
a check valve between the diversion and the backflow
preventer.
Passage :
distance adapted to
maintenance operations
H
H
Internal
Distribution
0,5 mini
1,5 maxi
1
2
Set of protection BA009MC
DN
H
REF
mm
mm
2231722MCK
65
247,34
2231822MCK
80
270,51
2232300MCK
100
352,52
2232400MCK
150
405,06
2232500MCK
200
485,7
2232600MCK
250
485,7
EN
ø
F).
3
LT
ØF
mm
mm
740
40
844
40
986
60
1224
60
1485
60
1631
60
Tabla de contenido
loading

Este manual también es adecuado para:

2231722mck2231822mck2232300mck2232400mck2232500mck2232600mck

Tabla de contenido