Periodical inspection
To ensure proper operation of the unit, it is necessary to have an annual inspection carried out by qualified personnel,
providing for the following:
•
heat exchanger check and cleaning with suitable products if dirty or clogged
•
check and possible cleaning of burner (do not use chemical products or wire brushes)
•
check and cleaning of electrodes, which must be free of deposits and properly positioned
•
seal and gasket check (burner, sealed chamber, etc.)
•
check and cleaning of sludge remover filters and system filters
•
check, cleaning and filling of condensate drain traps
•
check of wiring, contacts, electrical actuators
•
check and cleaning of generator air inlets and boiler room air intakes
•
check and cleaning of fume evacuation duct-manifold-flue system.
•
expansion tank check and prefilling
•
check of correct and stable system water pressure, ensuring conformity with the required working pressure.
The use of automatic filling systems for reinstatement of operating conditions
B
must provide for adequate treatment of the water (ref. "System water characte-
ristics" on page 311 )
•
check of heating system water chemical and physical parameters (ref. "System water characteristics" on page 311 )
•
water and gas system tightness check
•
check of correct and stable gas supply pressure to plant (20 mbar for operation with natural gas); any fluctuations
or pressure drops below the declared value can create malfunctioning and stops with need for manual resetting.
•
burner ignition and control and safety device check (gas valve, flowmeter, thermostats, etc.)
•
circulating pump check, freeing when necessary
•
fume analysis and check of combustion parameters
The casing, control panel and aesthetic parts of the boiler can be cleaned with a soft damp cloth, possibly
A
soaked in soapy water. All abrasive detergents and solvents should be avoided.
Opening the casing
To open the boiler casing:
1. Undo the screws A.
2. Slide the cover towards the back so as to hook the pin as shown in the box in fig. 86.
338
A
fig. 86- Cover opening
cod. 3541V120 - Rev 00 - 09/2021