Typical "Pedestal / Island" Installation
WARNING! Threaded pipe joints and connections should be sealed with the
appropriate sealant or sealant tape to minimize the possibility of leaks.
Materials:
1-1/4" threaded suction pipe, cut to extend 32-1/2" above the island.
FRPA125 Pedestal Kit (includes Pedestal Pipe, Base, & Coupler).
Threaded pipe joint sealant appropriate for application.
Installation Procedure:
1)
Remove the coupler
from the pedestal pipe
by loosening the set
screws.
2)
Slip the pedestal pipe /
pump base assembly
over the 1-1/4" suction
pipe.
3)
Loosen the screws in
the pedestal base to
allow the pedestal pipe
to slide down exposing
the end of the suction
pipe.
4)
Screw the coupler onto
the suction pipe; seal
threads liquid tight with
appropriate thread
sealant.
5)
Slide the pedestal pipe
into the coupler and
tighten the set screws.
6)
Tighten the screws in
the pedestal base.
7)
Mount the pump on the
coupler and seal
threads liquid tight with
appropriate thread
sealant.
Additional specifications on page 15.