ASSEMBLING THE PANELS
MOD. 92÷300
Sequence:
a) Position the bottom side panels (pos. 1 and 2), hooking them to the supports on the boiler. To know which of the two sides is
the right or the left, refer to the hole for the cable gland plate (pos. 6), which must be facing the front of the boiler.
b) Fasten the control panel to the top panel (pos. 3).
c) Rest the top panel (pos. 3), complete with the control panel, on the side panel (pos. 1), complete with springs, closing pins and nuts
(pos. 10-11-12) .
d) Insert the bulbs of the instruments into the sheaths (as shown on page 41), and make the electrical connection between the
control panel and the power line, burner and any pumps etc. The probes should be inserted fully into the corresponding
sockets, to improve contact. Then secure the capillary tubes with the springs. Close the cover on the electrical panel, pass the
burner plug through the side plate (pos. 6) and secure the cable with the cable gland supplied. Fasten the plates (pos. 6) with
the screws (pos. 7).
e) Fit the top panel (pos. 4) to the side panel (pos. 2) complete with springs, closing pins and nuts (pos. 10-11-12).
f ) Fit the rear panel (pos. 5) to the boiler using the screws (pos. 9) and the nuts (pos. 8). The panel must be fitted before installing
the burner.
g) Fasten the rating label to the boiler (see page 36), after having cleaned and degreased the part in question using a suitable
solvent, and apply it so as to ensure perfect adhesion. Do not remove the rating label, as it will lose its adhesiveness.
The rating label is included in the document envelope.
- 51 -
INSTALLATION