LCD display in L1-phase
Step 5: If there is no more fault alarm, the system to support 3-phase equipment is
completely installed.
Step 6: Please, switch on all breakers of Line wires in load side. This system will start to
provide power to the load.
NOTE: To avoid overload occurring, before turning on breakers in load side, it is better
to have whole system in operation first.
NOTE: Transfer time for this operation exists. Power interruption may happen to
critical devices, which cannot bear transfer time.
7.3 Start-up of single-phase equipment in parallel
Step 1: Check the following requirements before starting:
-
Correct wire connection
-
Ensure all breakers in Line wires of load side are open and each Neutral wires
of each unit are connected together.
Step 2: On the bottom panel of inverter, there are 5 pins DIP switches, you can set it as
shown in the image below.
NOTE: If there are two inverters in parallel, you only need to set inverter 1 and 2.
NOTE: It is necessary to turn off the inverters when setting the DIP switches.
Otherwise, the setting cannot be programmed.
Step 3: Turn on each unit.
LCD display in Master unit
LCD display in L2-phase
LCD display in Slave unit
70