Commissioning
General Commissioning
Before connecting the wallbox to the vehicle:
1. Clean the connection zone.
2. Check wall mounting for stability.
3. Check that all screws and terminal con-
nections are tight.
4. Make sure there are no knock-out holes
for cable routing left open. Seal them
with blind plugs if there is no cable routed
through them.
5. Make sure all cable glands are tightly
closed.
6. Perform visual inspection according to
commissioning protocol.
Maintenance
The owner of the wallbox is responsible for the maintenance
of the charging station, whereby both the law regarding the
safety of persons, animals, and property must be observed, as
well as the installation regulations in force in the country of
use.
1. Dirt and natural organic matter on the outside of the char-
ging station can be cleaned off using a damp soft cloth.
2. Check the charge plug for damage and for foreign matter.
Clean if necessary.
3. Have the wallbox and its installation inspected by an elec-
trician on a regular basis and in compliance with your local
country installation guidelines.
7. Switch on the input power to the wall-
box.
8. Check HMI LED status indication.
9. Perform electric commissioning accor-
ding to commissioning protocol and
normative requirements and additio-
nal local installation requirements (if
applicable).
10. Perform functional tests with a simula-
tor or an EV and simultaneously check
HMI LED status indication.
11. Fill-in commissioning report.
If you need a commissioning report, find an
example of it at www.elli.eco/download.