SMA INVERTER MANAGER Instrucciones De Instalación página 27

Ocultar thumbs Ver también para INVERTER MANAGER:
Tabla de contenido
Idiomas disponibles
  • ES

Idiomas disponibles

SMA Solar Technology AG
INFORMATION
It is essential to choose the correct grid code. A
modifcation after the f rst ten operating hours
have passed is only possible with a personal
SMA Grid Guard code.
The grid code parameters can be changed
subsequently with the LCS-Tool (see
Section 5.2.11, page 38). Prerequisite is the
use of the latest version of the LCS-Tool.
igure 15: LCS-Tool - selecting the country and grid code
☑ A list of the identifed inverters of the selected
Inverter Manager is displayed.
11. Make sure that all inverters are present. It is
possible to continue the confguration of the
listed inverters even if not all inverters are
detected. The undetected inverters can always
be confgured later.
Installation Manual
8. Select the desired grid code from the list of
options available for the selected country.
9. To load a customer-specifc country data set
(JSON fle), select the Open icon under Grid
code selection (Open icon: button (A) in
fgure15).
10. The LCS-Tool shows a summary of the previous
settings and asks for confrmation. A wrong
confguration can be changed by clicking the
[Back] button and by changing the settings in
the previous window.
☑ Inverters that have not been commissioned (no
grid code assigned) are presented with a blue
square together with their software version.
12. Select the inverters to be commissioned and
select the [Add] button.
☑ A green square identifes the commissioned
inverters. The inverters are only connected to
the utility grid when the [Start] command has
been carried out from the bar below the start
menu.
IMVIOBOX-IA-xx-18