Conveyor Set-Up
1. . .
Mark a chalk line on floor to locate center of the
conveyor (Floor Mounted Conveyors).
2. . .
Place the drive section in position.
3. . .
Install remaining sections placing end without support
on extend support of previous section (Figure 6A and
8A). Check "Match Mark" Numbers to see that
adjoining sections are in proper sequence
4. . .
Fasten sections together with splice plates and pivot
plates (Figure 8B). Hand tighten bolts only.
5. . .
Check to see that conveyor is level across width and
length of unit. Adjust supports and ceiling hangers as
necessary.
6. . .
Install electrical controls and wire motor. See Page
10.
7. . .
Install and track belt per instructions on Pages 9 and
18.
FIGURE 8A
DRIVE SECTION
(SECCION DE LA
UNIDAD MOTRIZ)
8
INTERMEDIATE
SECTION
(SECCION
INTERMEDIA)
"MATCH-MARK"
NUMBERS
(ETIQUETAS DE
ARMADO)
Montaje del
Transportador
Marque con tiza una línea en el suelo para ubicar el
1. . .
centro del transportador.
2. . .
Coloque la sección motriz en su posición.
3. . .
Instale las secciones restantes colocando el extremo
sin soporte en la placa pivote del soporte de la
sección anterior (Figura 6A y 8A). Revise las
etiquetas de Secuencia de Armado para asegurarse
que las secciones unidas estén en el orden correcto.
4. . .
Asegure las secciones con placas de empalme y
placas pivote (Figura 8B).
manualmente.
5. . .
Revise si el transportador está nivelado a lo ancho y
largo de la unidad. Ajuste los soportes a piso o a
techo como sea necesario.
6. . .
Instale los controles eléctricos y conecte el motor.
Vea la página 12.
7. . .
Instale y alinee la banda siguiendo las instrucciones
en las páginas 9 y 18.
FIGURE 8B
SIDE CHANNEL
(CANAL LATERAL)
MOUNTING BOLT
(TORNILLO DE MONTAJE)
SIDE CHANNEL
(CANAL LATERAL)
Apriete los tornillos
SPLICE PLATE
(PLACA DE EMPALME)
PIVOT PLATE
(PLACA PIVOTE)
STATIONARY
SUPPORT
(SOPORTE
ESTACIONARIO)