Página 1
Escriba aquí el número del modelo comprado. Conserve estas instrucciones para usarlas en el futuro. Inscrivez le numéro de modèle ici. Conservez ces instructions pour consultation. 36” x 36” 40064 48” x 34” 48” x 34” B67311-4834-WH 40084 60” x 32”...
REQUIREMENTS FOR SUCCESSFUL INSTALLATION KNOWLEDGE BASE: Framing Plumbing These instructions include suggestions for rough construction and plumbing installation. Local building codes vary and could supersede those suggestions. If you are not confident in your ability to perform these tasks, contract out those tasks you need help with or use a professional installer.
TOOLS AND MATERIALS REQUIRED • 2” x 6” and 2’ x 4” lumber for additional wall studs • Lumber for bracing • Rags or padding to protect product during bracing NOTE: It is recommended to install insulation. HERRAMIENTAS Y MATERIALES NECESARIOS •...
ROUGHING-IN Rough plumbing must be installed before panel installation. For masonry construction, floor and walls must be framed to accommodate plumbing and installation. Studs should be located as shown below. CONEXIÓN DE CAÑERÍAS Deben instalarse las cañerías antes de instalar el panel. Para los trabajos de mampostería, el piso y las paredes deben acanalarse para dar lugar a las cañerías y la instalación.
Página 6
Place drop cloth in shower base to protect surface while installing Measure and mark location for plumbing fixtures on back of side panel. shower walls. Using proper size hole saw, cut out plumbing fixture holes from back Position back panel, leaving an even gap on both sides of back panel. side of panel.
Página 7
Back side of panel. Parte posterior del panel Face arrière du panneau. To apply fire retardant pad, remove backing from self-adhesive pad. Install side panels pushing in and down until panel tops are even and curved area on side panel fits against back panel. Center pad over mixing valve hole and press firmly onto back side of panel.
Página 8
Using a pencil, mark panel height on all wall studs. Apply Adhesive to back studs up to pencil line. Remove panels. Apply sealant along back of base. Con un lápiz, marque la altura del panel en todos los montantes de la Aplique adhesivo para respaldar los montantes hasta la línea en lápiz.
Página 9
Press back panel in place. Apply adhesive to side studs up to pencil line.. Gaps between flanges and studs must be less than 1/8”. Insert shims to fill gaps. Apply sealant along side of base and back panel. Secure top flanges to studs with 1-1/4” screws. Use panhead or roundhead screws.
Página 10
Install side panel, sliding the side panel into gap between wall and back Install temporary braces to hold side panels tight against studs while panel, pressing firmly into corner and against studs. Push in and down adhesive dries. until panel tops are even and curved area on side panel fits against back panel.
CARE AND CLEANING For regular cleaning use ONLY mild detergents or warm, soapy water. Use ONLY non-abrasive cloth or sponge. Always rinse surfaces after cleaning. Before cleaning this product with cleaning products, test a small, inconspicuous area. Manufacturer does not recommend the use of cleaning products that contain any of the following chemicals.
LIMITED WARRANTY All parts and finishes of the Delta® Shower Wall unit are warranted to the original consumer purchaser to be free from defects in material and workmanship for the time periods listed below. Delta recommends using a professional plumber for all installation and repair. Delta will replace, FREE OF CHARGE, during the warranty period, any part or finish that proves defective in material and/or workmanship under normal installation, use and service for the time period listed below: •...