5.10.1 Electrical system carried out by the factory
Key
C
Capacitor
CN1
Probe connector
E
Electrode
h..
Hour counter
MV
Motor
PA
Minimum air pressure switch.
PG
Minimum gas pressure switch
RS
Remote reset
SO
Ionisation probe
S3
Lockout signal (230V - 0.5A max.)
T6A
Fuse
TB
Burner earth
TL
Limit thermostat
TS
Safety thermostat
V10
Safety valve
V11
1st stage valve
X..
Plug
XP..
Socket
Master
switch
230V ~ 50Hz
Installation
Do not invert the neutral with the phase in the
Check that the electrical supply of the burner
WARNING
The section of the conductors must be at
Check the burner stops by opening the thermo-
stats and check it locks out by opening the con-
nector (CN1) (Fig. 18) inserted in the probe's red
wire, located on the outside of the control box.
WARNING
If the cover is still on, remove it and proceed with
the electric wiring following the wiring diagrams.
Use flexible cables in compliance with EN 60 335-
CAUTION
1 standards.
23
GB
CARRIED OUT
IN THE FACTORY
TO BE DONE BY
BY THE INSTALLER
D4626
electrical supply line.
corresponds to that shown on the identifica-
tion label and in this manual.
2
least 1mm
. (Unless requested otherwise by
local standards and legislation).
Fig. 18
20136130