3.2 - MONTAGGIO
CWX3-5
•
Use the drilling template provided (2) to determine the
position of the suspension rods (1).
•
The template must be placed between 2 "T" rails of the
false ceiling.
•
Install the suspension rods (not supplied).
•
Place the side where the connections are located in
the most appropriate position.
•
The "T" rail (3), located on the electrical box side, must
be temporarily removed.
•
Put the unit in place and check that it is level.
•
Adjust the distance between the unit and the false
ceiling (5) (max. 23 mm) by using the suspension rod nuts.
•
Also check the distance between the suspension flange (6) and the ceiling (7) (min. 41 mm). A lesser
distance may create noise if the unit touches the ceiling.
3
2
544 x 506
4
CWX6-8-10
• Use the drilling template provided (2) to determine
the position of the suspension rods (1) and the hole
to be made in the false ceiling (figure 01).
For the suspension rods, use dia. 8 or 10mm
threaded rod.
• Refer to the dimensions in the table opposite (figure
02).
• Install the suspension rods (not supplied).
• The length of the suspension rods must be long
enough to have distance of more than 15 mm
between the bottom of the suspension rod and the
bottom of the unit (figure 01).
• Place the side where the connections are located in
the most appropriate position.
• Install the unit on the suspension rods using the
nuts and washers (figure 03).
• Check that the unit is level.
• Adjust the distance between the unit and the top of
the false ceiling (48 mm) using the nuts on the
suspension rods (figures 01 and 03).
• Remove the protective cardboard from the fan.
Nuts and washers
(2 assemblies)
Lock nut
figure 03
Suspension rod
10
Top
Bottom
Suspension flange
48
1
1
2
figure 01
A
B
Model
820
566
CWX 6
1110
856
CWX 8/10
A (ceiling hole dimensions)
B (centre-to-centre distance
between suspension rods)
Centre of the
grille
figure 02
544
10
10
6
7
5
1
2
X
Condensate
drain tube
Hydraulic
connections
GB
5