Installing The Base Box - Erreka TOPO Manual Del Instalador

Accionador electromecánico soterrado para puertas batientes
Tabla de contenido
Idiomas disponibles
  • ES

Idiomas disponibles

INSTALLATION
4

INSTALLING THE BASE BOX

Assembly positions and dimensions
Dimension A: minimum 60mm
Dimension B: 56mm
Dimension A: distance between the rotation axle of
the gate and the pillar.
Dimension B: Height from the ground to the lower
part of the gate.
Dimension C: Height of the base box.
Dimension D: Height of the drainage ditch.
Fig. 4
Installation dimensions
Procedure
Dismount the gate and prepare the pit
50
Installation manual
Dimension C: 152mm
Dimension D: 20mm approx
P02A
Fig. 5 Base box dimensions
The lower hinge (1) shall be eliminated during
installation, in order to prevent misalignment.
Bear in mind that the upper hinge (2) must be on the
upright of the pivot (3) of the base box.
1 Dismount the gate (1).
Use appropriate means to raise the gate
safely.
2 Eliminate the lower hinge (2).
3 Dig the pit, (3) respecting the dimensions indicated.
4 Place stones and gravel at the bottom (4) in order to
achieve a permeable base which facilitates drainage.
5 Dig the clearances for the electrical ducts (5).
6 Dig the clearances for the drainage ducts (6).
The drainage ducts must slope downwards.
Tabla de contenido
loading

Tabla de contenido