5.1 Measures Before Commissioning
The following measures must have been performed prior to commissioning:
Measure
Operate the hardware
according to specification
Check the proper
installation of the
measuring system
Clean the coded band
during commissioning.
Check the measuring
system prior to
commissioning
5.2 Status LED
A LED signals the status of the device:
Display
LED off
LED green
LED green flashing
LED red
LED red flashing
5.3 Error mode
In case of error an error code is output and the measuring system locks (Locked mode);
positions are no longer transmitted. In this case, the sensor can only be reset by an evaluation
unit. The evaluation unit can also be part of the elevator control, which can/is permitted to carry
out the reset.
Additional information can be found in the following documents:
• for LES02 (R67073)
64 | EN
Description
The operating conditions are defined in the operation manual and
in the manual and must be complied with.
The V2A coded band must be mounted fixedly in the top and the
bottom of the elevator shaft; it must be sufficiently secured against
slipping.
The tension force must be 100 ... 150 N [22.48 ... 33.72 lbs].
The lateral distance from the coded band to moving parts must be
at any point at least 50 mm [0.16 ft].
Sensor oscillation in the transversal direction shall not exceed
10 mm [0.03 ft].
The coded band must be checked for dirt and foreign bodies and
cleaned during commissioning.
In every new installation, the sensor must run once along the
whole installed coded band in order to check the complete system
for errors or wrong installation.
LED
Meaning
No voltage
Supply voltage applied to device
Communication present on bus
Sensor in Locked mode
An error occurred that did not result in Locked mode.