15. HYDRAULIC CONNECTIONS
The drain must be connected by means of a suitable siphon, ensuring that it is free and the rubber
has not impediments and obstructions. The condensate drain system must be sized for proper
operation; in all the sections of piping that constitute the drain connections to the sewer system,
the water fl ow must be entrusted mainly to the weight of the liquid, without creating signifi cant
pressures or depressions and capable of altering the regular functioning of the fl ow.
Note: if a direct connection is created with the external environment, air is sucked in, which can
obstruct the fl ow of condensate. Avoid the use of a double siphon or that the siphon is laid forming
many curves, as this obstructs the fl ow of condensate.
16. AERAULIC CONNECTIONS
The duct connections should be made through circular ducts with the same diameters as those pro-
vided on the machine. The technical sizing of the ducts will still be carried out as function of the plant
and of the pressure of the heat recovery unit. The machine is not equipped with anti-vibration joints
internal joints on the attack so we recommend preparing these ducts in order to avoid any vibration.
17. VERIFICATION OF CURRENT CONSUMPTION
At full speed , check that the current consumption complies with the limits of the plate expressed in
the case of abnormal consumption turn off the fan and contact our support department.
Warnings:
• All wiring and electrical components used for the installation must comply with the regulations
in force;
• The power line must be made in accordance with the regulations in force;
• Wiring must be done by qualifi ed technicians electricians;
• The current consumption must comply as set out in the data plate
18. OPERATION AND USE
Before operating the machine, make sure that the discharges are free, that the air duct systems is
free and, if present, appropriately dampers tuned.
S1 = 50 mm
S2 = 25 mm
minimum compliance measures