Commissioning/Decommissioning

6.1

Commissioning

NOTICE
The pump may not be turned on if there is no guarantee that the
BADU OmniTronic will take control of the pump. It must also be
ensured that the pump does not turn on when the valve is turning.
Close the transparent lid bevor the device is connected to the
power supply.
6.1.1

Switching on

Do not switch on the device until the drive box is fully connected
to the electronics.
The screws of the lid must be firmly tightened so that the
correct distance from the keyboard is kept.
Fit the lid carefully and in the correct position so that the
keyboard is not damaged.
6.2

Functional test

6.2.1

Test cycle

Once the supply voltage has been applied and the control has
been turned on with the illuminated rocker switch, the device runs
a test cycle. This ends in the position "Filter". Then the device is
ready for operation.
6.2.2

Shut-off valves

The integrated shut-off valves in the control connection lines must
be opened completely.
03|2022
Commissioning/Decommissioning
EN 49
Tabla de contenido
loading

Productos relacionados para BADU OmniTronic Serie

Este manual también es adecuado para:

Omnitronic r41Omnitronic r51

Tabla de contenido