Installing the Zoneline
1. Plan for proper electrical supply, drains and ductwork
locations.
2. Install the louver and wall plenum.
3. Install and level the drain platform.
4. Complete condensate drain connections.
5. Install unit to wall plenum.
6. Connect the top ductwork.
1. Plan for proper electrical supply, drains and ductwork locations.
1. Complete rough in plumbing for primary and secondary condensation drains.
2. Install the Louver and Wall Plenum
1. Install the louver to the wall plenum.
Refer to instructions included in the louver kit RAVAL4 for proper installation procedures.
2. Adjust depth of wall plenum and install into exterior wall.
Refer to instructions included in the wall plenum kit RAVWPT15B for proper installation procedures.
3. Install and Level the Drain Platform
1. Refer to instructions included with Drain Platform kit RAVDPLAT for proper procedure for support and
installation of platform to wall plenum. Platform must be level in all directions.
Condensate Disposal System
The Condensate Disposal System increases energy efficiency utilizing a factory installed fan that slings the
condensate onto the hot outdoor coil.
When high outdoor humidity prevents the slinger from disposing of all condensate, the excess condensate overflows
into the condensate drain pan and out the 3/4" internal drain connections.
NOTE: If the primary drain system fails to remove all of the condensate from the unit, any excess condensate
will overflow from the drain pan into the secondary drain (if connected), and drain outside the building. This
is your indication that the chassis or drain requires servicing.
49-5000640 Rev. 1
INSTALLATION SUMMARY
INSTALLATION INSTRUCTIONS
7. Connect the remote thermostat.
8. Connect auxiliary features, if required.
9. Make electrical connections to unit.
10. Install filter.
11. Review the final installation checklist.
12. Turn power on.
13. Adjust auxiliary control settings, if required.