Chapter 5. Machine installation
5.1. Transport and positioning
Handle with great care during transport and positioning!
Before any movement, make sure that the lifting means is suitable for the load to be lifted!
Cut the strap with scissors make sure
you protect your eyes by wearing
glasses and withdraw the cardboard.
Remove the screws and any plate
intended to fasten the machine to the
pallet.
Using a fork lift, remove the tunnel from
its pallet and level it on the ground.
Hook the panels (C) to the machine (for
mod. Tunnel 50 Twin only).
Remove the box containing the roller
conveyor (19) and couple it to the
conveyor belt.
5.2. Environmental conditions
Place the machine level on the floor in a suitable environment free from humidity, gases, explosives, combustible
materials. The machine may only be installed on smooth, flat non-inflammable surfaces.
Leave a minimum space of 0,5m around the machine so that not to obstruct air inlets.
Once the correct position is achieved, lock the machine by means of the wheel brakes.
Working environment conditions:
Temperature from + 5°C to + 40°C
Relative humidity from 30% to 90%, without condensation
The lighting of the operation room shall comply with the laws in force in the country where the machine is installed.
However, it shall be uniform and allow good visibility in order to safeguard the operator's safety and health.
MACHINE PROTECTION FACTOR = IP20
THE AIRBORNE NOISE MADE BY THE MACHINE IS LOWER THAN 70 dB(A)