3.
Slide the battery trays into the chassis (see Figure 9).
4.
Secure the battery trays to the chassis with the battery retaining
bracket and screws provided in the P64 accessory kit (see
Figure 10).
5.
Install the UPS front covers (see Figure 11).
NOTE The upper front cover is provided in the P64 UPS carton and the lower front cover is
provided in the P64 accessory kit.
6.
If you are installing the UPS as a standalone cabinet or in a tower
configuration, continue to the following section, "Tower Setup."
If the UPS is in a rack and you are installing an optional EBM,
continue to "EBM Installation" on page 15; otherwise, continue to
"Power Connections and Startup" on page 21.
®
EATON Powerware
9125 (9910-P64) UPS Installation Guide for IBM
Figure 9. Installing the Battery Trays
Battery Retaining Bracket
Figure 10. Securing the Battery Trays
Figure 11. Installing the Front Covers
®
S
Applications
INSTALLATION
11
164201637 Rev A