Installation
Installation
NOTICE! Avoid cleaners containing organic
solvents, alcohols, and hydrocarbons.
Rinse with water after cleaning.
Supplies Required:
• (3) ³⁄₈" floor anchors and bolts
• Pipe sealant
• Piping to ½" NPT water supply inlet
• Piping to 1¼" NPT drain outlet
• Sign-mounting hardware
Local codes may require the installation of
a backflow prevention valve to complete
proper installation. Compliance with local
codes is the responsibility of the installer.
Valve must be tested annually to verify that
it is functioning properly. Backflow prevention
valves are not included with the fixture
and may be supplied by the contractor or
purchased from Bradley Corporation.
Step 1: Secure base to floor
1. Install three suitable anchors (supplied by
installer) for ³⁄₈" bolts in the floor.
2. Bolt the base to the floor anchors using ³⁄₈"
bolts (supplied by installer).
Step 2: Assemble eyewash
1. Assemble eyewash components as shown on
page 4.
• Apply pipe sealant (supplied by installer)
to all male-threaded pipe joints.
• Use the rubber grip pad provided or
a strap wrench around pipes when
tightening to prevent marring. Place the
grip pad on the pipe, then put the wrench
over the grip pad and turn the pipe with
the wrench.
Step 3: Connect water supply
1. Connect the water supply piping (supplied by
installer) to the ½" NPT inlet on the eyewash.
2. Connect the drain piping (supplied by installer)
to the 1¼" NPT drain outlet on the eyewash.
3. Mount the safety sign to the wall using sign-
mounting hardware (supplied by installer).
Bradley • 215-155Y Rev. L; ECN 12-05-003C
(273mm)
8¹⁄₈"
(206mm)
36"
(914mm)
to Bottom
of Base
All dimensions assume standard thread
engagement. Variations in manufacturing allow
for +/- ¹⁄₈" (3mm) per threaded joint. To find
the tolerance of a dimension, add the number
of thread joints in between a dimension and
multiply it by ¹⁄₈" (3mm).
10/18/2012
15⁷⁄₈"
(403mm)
Ø 10¾"
5¼"
(133mm)
6"
(152mm)
S19-210Y
42½"
(1079mm)
to Bottom
of Base