Installation
Installation
Supplies Required:
• (3) 3/8" floor anchors and bolts
• Pipe sealant
• Piping to 1/2" IPS water supply inlet
• Piping to 1-1/4" IPS drain outlet
• Sign-mounting hardware
Step 1: Secure base to floor
1. To secure base to floor, install three suitable
anchors (supplied by installer) for 3/8" bolts in
the floor (Figure 1).
2. Bolt the base to the floor anchors using 3/8"
bolts (supplied by installer).
Step 2: Assemble eyewash
1. Assemble eyewash components as shown in
Figure 2a on page 4 (for unit with plastic bowl)
or Figure 2b on page 5 (for unit with stainless
steel bowl).
• Apply pipe sealant (supplied by installer) to
all male-threaded pipe joints.
• Use the rubber grip pad provided or a strap
wrench around pipes when tightening to
prevent marring. Place the grip pad on the
pipe, then put the wrench over the grip pad
and turn the pipe with the wrench.
Step 3: Connect water supply
1. Connect the water supply piping (supplied by
installer) to the 1/2" IPS inlet on the eyewash.
2. Connect the drain piping (supplied by installer)
to the 1-1/4" IPS drain outlet on the eyewash.
3. Mount the safety sign to the wall using sign-
mounting hardware (supplied by installer).
4. Open the water supply lines and test for leaks
and adequate water flow.
NOTE:
All dimensions assume standard thread
engagement. Variations in manufacturing allow
for +/- 1/8" (3mm) per threaded joint. To find
the tolerance of a dimension, add the number
of thread joints in between a dimension and
multiply it by 1/8" (3mm).
Bradley Corporation • 215-155 Rev. V; EN 06-532D
S19-210
15-1/2" (394mm)
Ø 10"
(254mm)
7-3/8"
(187mm)
5-1/4"
(133mm)
36"
(914mm)
S19-210B
15-1/2" (394mm)
Ø 10-3/4"
(273mm)
7-3/8"
(187mm)
(133mm)
36"
(914mm)
Figure 1
6/26/07
S19-210, S19-210B
41-1/2"
(1054mm)
6"
(152mm)
5-1/4"
41-1/2"
(1054mm)
6"
(152mm)
3