BOX INSTALLATION PROCEDURE
Dig a hole big enough to hold the box containing
the operator (see F1)
Insert the tubes for water drainage in the prepared
holes (F1C)
Insert the sheath for laying the power cables and
limit switch (F1D).
Note: while positioning the box, keep in mind the
minimum distance there must be between the pil-
lar and the centre of rotation of the gate hinge. (see
F2)
Cement so that the box cannot be moved, wait for
it to dry and then assemble the operator and levers.
EI40
11/24
Distance between
Pillar - Hinge Centre