8.2 Download and Install the SunPower One app
1.
Android device users can download the SunPower One app from Google Play.
2. iOS device users can download the SunPower One app from the Appstore
TIP
8.3 Commissioning SunPower Reserve
Before commencing, ensure that the Reserve system is correctly installed and has a functional
data connection.
Below is a summary of the steps required to successfully commission the SunPower Reserve.
Please refer to the following instructions:
1.
Launch the SunPower One app and log in using your SunPower One username (email) and
password.
2. On the home screen, tap „start" to initiate the commissioning process for a new system.
3. On the subsequent screen, enter the email address of the customer for whom you are
installing the system. This email will be utilized to pre-configure the customer account
required for logging into the SunPower One app. It is crucial to verify the accuracy of the
email with the customer and ensure that they can access it on their mobile device.
4. Select the appropriate system configuration as outlined in section 3.3, and follow the app's
provided steps to complete the activation and configuration of your installation.
5. Once the Reserve setup is complete, a confirmation email will be sent to the customer. This
email will contain a link to the SunPower One app, enabling the customer to activate their
SunPower One account and enjoy the comprehensive SunPower One experience.
Please follow the above steps to effectively commission the SunPower Reserve system.
CAUTION
© 2023 Maxeon Solar Technologies, Ltd. All rights reserved. | 547143 Revision B - June 2023
Specifications included in this document are subject to change without notice
Commisioning tools including login details are only available to installers
that have completed the necessary training modules.
The safety standard must be set correctly
If you select a safety standard which is not valid for your country and
purpose, it can cause a disturbance in the energy storage system and lead
to problems with the grid operator. When selecting the safety standard,
you must always observe the locally applicable standards and directives
as well as the properties of the PV system (e.g., PV system size, grid
connection point). If you are not sure which safety standard is valid for
your country or purpose, contact your grid operator for information on
which safety standard is to be configured.