6. Commissioning, operation
Option screw built-in variant
GB
Commissioning
During the commissioning process pressure surges must be avoided
■
at all costs
Install the pressure connection according to the symbols
■
⊕ high pressure ⊖ low pressure
Use the pressure gauge only if the diaphragm is undamaged and if it
■
is in perfect condition with regard to safety.
10
After fitting the measuring element into the case
it can be moved in a clockwise and counter-
clockwise direction respectively for 15 angular
degrees in order to ensure precise horizontal
positioning of the instrument.
WIKA operating instructions air2guide model A2G-05