LIFT CORPORATION Sht. 6 of 16 DSG#
Check operation of foot guard switch mechanism before operating liftgate.
9. Stand on platform, then raise
platform above ground as shown
in FIG. 6-1.
10. Check operation of switch mechanism by
lifting bar at the RH end (FIG. 6-2) until
a click is heard. While holding the bar
up, hold the UP-DOWN toggle switch in
the RAISE position. Platform should not
raise. Then, hold the UP/DOWN toggle
switch in the LOWER position. Platform
should lower.
11. Lower bar until a second click is heard
(FIG. 6-2). Hold the UP-DOWN toggle
switch in the RAISE position. Platform
should raise. Then, hold the UP-DOWN
toggle switch in the LOWER position.
Platform should lower.
12. Repeat the last two steps for the middle
and LH positions (FIG. 6-2).
© MAXON Lift Corp. 2018
M-16-01
CAUTION
GROUND
LH
BAR LIFT LOCATIONS
Rev. A Date: 08/23/18
3"
RAISE PLATFORM
FIG. 6-1
UP-DOWN
SWITCH
BAR
MIDDLE
FIG. 6-2
RH