Monogram FZIR360NNRH Instrucciones De Instalación página 16

Tabla de contenido
Idiomas disponibles

Idiomas disponibles

Installation Instructions - Standard Installation
STEP 4 INSTALL ANTI-TIP BRACKET (Cont.)
Line on Wall
Center
• Mark an additional hole at each end of the bracket. If one
of the studs is closer to the end of the bracket, mark an
additional hole towards the center of the bracket.
• Drill 1/2" (1.27 cm) holes into the wall board at the loca-
tions marked for the toggles to be mounted (not the stud
markings).
• Drill 3/16" (0.47 cm) holes into wooden studs where
marked. If steel stud construction, drill 1/2" (1.27 cm)
holes into the studs where marked. You will use 2 tog-
gles with the metal studs.
Install Wall Toggles:
The wall toggles and bolts can be ordered as Service Kit
#WR49X10193. Wall toggles are installed in the drywall
and metal studs for stability. Install the wall toggles as
follows:
• Drill 1/2" (1.27 cm) holes at the wall markings made in
the holes at the ends of the wall bracket.
• Hold the metal channel flat against the plastic straps
and slide the channel through the hole.
Plastic Straps
• Gently pull back at the ends of the plastic straps to
make the channel rest flush behind the wall.
• Hold the ends of the
straps in one hand and
slide the plastic cap
along the straps until
the flange of the cap is
flush with the wall.
• Place your thumb between the
plastic straps and bend up and
down to snap the straps off at
the wall.
Metal Channel
Cap
Install Screws and Bolts:
• Have someone hold the wall bracket centered in place
with each of the holes aligned with the correct opening
in the bracket and level with the horizontal line.
• Insert the lag screws through the bracket and into the
stud. Tighten with a wrench.
Lag Screw
Anti-Tip Wall Bracket
• Insert the bolts into the toggle by hand until snug.
Tighten with a wrench.
Bolt
Anti-Tip Wall Bracket
16
Wood Stud
Drywall or
Steel Stud
Wall Toggle
31-1000416 Rev. 0