Supplied Equipment; Equipment List - What's Needed - Ford Pro Guia De Instalacion

Tabla de contenido
Idiomas disponibles

Idiomas disponibles

Supplied Equipment

1 – 80A Charger
1 – Mounting Bracket
2 – 3/8" x 2-1/2" LG Flange Hex Head Lag Bolts
6 – (T20) Torx-head Dog Point Screws – M4 x 0.7 x 16 mm (2 extra)
1 – Connector – 3 position (Communications)
1 – Connector – 2 position (Dark Start – Battery Backup)
Equipment List – What's Needed
Certified Electrician
7/32" Drill Bit
Stud Finder
Level
CAT I – 600v Multimeter (minimum)
5/32" Hex Head Bit or Allen Wrench
9/16" Wrench or Socket Wrench
Small Flat head Screw Bit (For RS-485 Connectors)
Torx Head (T20) Bit
Torque Driver
Step Drill Bit – (If needed for Conduit Connectors – 1-1/8"- 1-3/8" holes)
1- ¾" Conduit Connector (see Installation Checklist If Needed)
1- 1" Conduit Connector (see Installation Checklist If Needed)
3 AWG – 90°C Copper wire should be used
NOTE: Wire must have a temperature rating of 90° C or higher for AC Connections (A/L1 and B/L2[N])
80A charger requires a 100 A non-GFCI breaker.
HVDC Wire – 8 AWG 90°C, 600V
Dark Start Wire – 16 AWG, 600V to comply with NEC300.3©(1).
Communication Wire – 18 AWG, 600V to comply with NEC300.3©(1).
Equipment
Hardware Kit
TOOLS
ADDITIONAL ITEMS (Not Included)
P a g e
| 6