8 Recommissioning the Inverter
• Connect all cables coming from the DC load-
break switch to the DC-EMV.
• Connect the cables to the AST. When doing so,
ensure that the assignment is correct.
5. Ensure that all cables are securely in place.
6. Recommission the inverter see section 8, page 18.
8
Recommissioning the Inverter
If you have disconnected the inverter from all voltage sources and want to recommission it, proceed
as follows.
Requirements:
☐ The circuit breaker must be correctly rated.
☐ The inverter must be correctly mounted.
☐ The DC connectors must be correctly assembled.
☐ The AC cable must be connected correctly.
1. Carry out the necessary tests according to the locally applicable laws, standards and
directives for the correct recommissioning after power assembly replacement. Take the
requirements for component replacements into account (see Section 2.2 "IMPORTANT
SAFETY INSTRUCTIONS", page 7).
2. Ensure that the grounding conductor in the inverter is correctly connected and functions
properly.
3. Mount the upper enclosure lid onto the enclosure and lightly fasten all screws.
18
DC-EMV-STPTLEE-10-RM-xx-10
SMA Solar Technology AG
Replacement Manual